3118 Trawick Rd
SCOPE OF OPERATION
Phase 1 Entrance
Phase 1 Stabilization
Phase 2 Stabilization #1
BANK RESTORATION 2
TEMPORARY CREEK CROSING 1
Phase 2 Stabilization #2
Remove & Restore Flower Bed
DEBRIS REMOVAL
CONSTRUCTION ENTRANCE
Repair Drainage Ditch
Phase 2 Stabilization #3
BANK RESTORATION 3
TASK EXECUTION ORDER
Raise MH 12”
1. WZTC 2. CONTRSUCTION ENTRANCE / SUPPLY STAGING AREA
3. *TEMPORARY CREEK CROSSING 1 4. *TEMPORARY CREEK CROSSING 2 5. *TREE REMOVAL 6. *BANK RESTORATION 1 7. REMOVE TEMPORARY CREEK CROSSING 2 8. *DEBRIS REMOVAL 9. REMOVE TEMPORARY CREEK CROSSING 1 10. *BANK RESTORATION 2 11. *BANK RESTORATION 3 12. FINAL RESTORATION 13. CONSTRUCTION ENTRANCE REMOVAL 14. WZTC REMOVAL
TEMPORARY CREEK CROSSING 2
Clear With Mulcher
BANK RESTORATION 1
TREE REMOVAL
Phase 2 Entrance
* Denotes a specific Work Order