SCOPE OF OPERATION
Raise MH 3’
Construction Entrance
Raise MH 6”
Touch up Class 7 and Class B
BANK RESTORATION 2
TEMPORARY CREEK CROSING 1
DEBRIS REMOVAL
CONSTRUCTION ENTRANCE
Replace netting and reseed
BANK RESTORATION 3
120’ of stabilization
TEMPORARY CREEK CROSSING 2
Install 24”x30’ permanent crossing
Install 24” x 30’ permanent crossing
BANK RESTORATION 1
Install 24” x 30’ permanent crossing
TREE REMOVAL
-Install 2 construction entrances -Raise SMH129063- 3’ -Raise SMH139842- 12” -Raise SMH174571- 6” -Touchup rock on NW corridor -120’ of bank stabilization -3 permanent crossing installations
Raise MH 12”