Business Process Maps SM - WD - RR
BusinessProcessMaps
SewerMaintenance -WaterDistribution - ResourceRecovery
Standardized BusinessProcessMappingSymbols
(OPEN)
Process
Describes theactivitypreformedbyaactor.
External Data
Describeswhenexternal data is introduced.
Describes apointwhere theactivity changesbasedupon thedecisionof theactor
Decision
(OPEN)
(OPEN)
PredefinedProcess
Describes aprocess that has alreadybeendefined.
(OPEN)
Database
Describeswhenadatabase isused.
Start/End
Document
Describes thebeginning (faucet) of process andend (sink)
Data
Describeswhendata isutilized
Describeswhena document isutilized.
Standardized BusinessProcessMappingTerminology
Actors -Makedecisionswithinabusiness.Organizations, Roles, People, Systems areActors.
Deliverables -Forms, DataandReports.
Activities/Tasks -Aprocess that canbeassigned toaactor.
DecisionPoints -Evaluates a specified conditionduring theprocess anddirects the flowofworkbasedon theevaluation.
Stop/End -Theactions that start and terminateaprocess.
CCTV Inspection - Call
SewerMaintenance
Workorders entered into Excel for daily tracking
Dailywork orders entered intoHansen
End
CCTVCrew CCTVSupervisor Assistant Superintendent Start
Supervisor notifies repair crew via Nextel/Radio
Yes
Supervisor receives and relays location to crew
Isdefect classifiedas an emergency?
No
Supervisor notifies repair crewvia writtenworkorder for completion in order of severity
Notifyhomeowner via spoken relayor informationor door hangerwhen appropriate
CrewPrintsout still photosormakes videoCD showing defects
Crew fills out paper workorder
Crewnotifies supervisor of pipe defects
Yes
CCTVCrewarrives and completes inspection
Dataentered into ITPipe software
Anydefects found?
No
CCTV Inspection–New Installation
SewerMaintenance
NotifiesCCTV supervisor to inspect givenarea
ReviewsDVD. Pipe pass inspection?
Start
No
Yes
CCTVCrew CCTVSupervisor Assistant Superintendent Engineer
Paperwork order entered intoHansen
Dailywork entered into Excel
End
Notifies engineer of completion viaemail andDVD
SendsCCTV crew to location
Crew completes paperworkorder
Arrives on site, completes evaluation
Copies inspection to DVD, notingany defects
CCTV Inspection - PM
SewerMaintenance
Monthly footage report distributed
Dailywork entered into Excel spreadsheet
Paperwork order entered intoHansen
End
CCTVCrew CCTVSupervisor Assistant Superintendent Start
Supervisor notifies repair crew supervisor for emergency repair
CCTV Supervisor gives locations to crew
Supervisor approves locations to televise
Yes
Defect Severe?
No
No
Crew completes paperworkorder
Crew commences withCCTV inspectionofmain
Conditionof pipegood?
Crewarrives on site
Yes
Complete inspection
EasementMainRepair and LightMaintenance
SewerMaintenance
Completedwork order entered intoHansen
Easement Inspector Repair Crew InspectionSupervisor Staff Support
Work completed entered into Excel
Gives easement inspector dailywork area
Start
End
Inspects area to verify inspectors assessment
Finisheswork, fills out paperwork order
Receives paperwork order from inspector
Fillsout paperwork request
Yes
Crew inspects area. Notes need for locate call andwhat equipment is viable
Fillsout paperwork order
Repair crew needed?
No
MainFlushCall
SewerMaintenance
Logs call information in spread- sheet
Receives call from staff or citizen
Start
FlushTruckCrew FlushTruckSupervisor Assistant Superintendent Dispatch/Staff Support
Notifiedof informationby staff support. Routes to supervisor
Paperwork order entered intoHansen
Dailywork entered into spreadsheet
End
Notifiedof informationby assistant superintendent. Routes to crew(s).
Receives call from crew. Either calls CCTV crewor Repair crewasnecessary.
CCTV Inspection– Call or Sewer Main repair
Yes
Crew receives informationand moves to site; begins flushing
Finish flushing line. Apprise supervisor andhomeowner of findings
Crew fills out paper workorder
Anything abnormal?
No
MainFlushPM
SewerMaintenance
Daily footages entered into logused for monthly flushing report
Dailywork entered into spread- sheet
Paperwork orders entered intoHansen
End
FlushTruckCrew FlushTruckSupervisor Assistant Superintendent Start
CCTV Inspection– Call or Sewer Main repair
Assigns area for crew to flush
Call CCTV crewor repair crew
Yes
Fillsout paperwork order
Highlights areas cleanedonmap
Flushes assigned area
Problem flushing line?
Continue tonext sectionof line
No
Easement Inspection
SewerMaintenance
Takephotos and document findings onworkorder
Submit to supervisor for regular inspection
Completes paper workorder
Undocumented aerial/main encountered
Inspects sewer easement
End
Start
SewerMaintenance CodeEnforcement EasementMaintenance Inspector Supervisor Easement Inspector
Document on spreadsheet for trending
Receives paperwork order
Sendwork requestwhere?
End
Haveeasement surveyedand staked
Verifywith code enforcement that easement exists
Cut easement (bush hog, hand cut or gyro cut)
Submitworkorder upon completion
End
todelineate boundaries
Code Enforcement Easement
Workorderwith attachedmap sent
End
clearing process
Homeowner (if any) isnotifiedby supervisor of impending repair/ constructionwork
Workorder sent to program supervisor for completion basedon severity
Crew fills outwork order as completed
Crew completes workonprojected date.
Yes
Workorder sent to assistant superintendent detailingproblem
Crew sent to flushor CCTV inspect the sewermain
Require repair?
Crew completes paperworkorder
Workorder entered into Hansen
Workorder recordedon spreadsheet
Crew finishes inspection/flushing
End
No
Inventory - Adjustment
SewerMaintenance
Start
Sends email to inventory manager detailing item number, quantity, truck number and reason for adjustment
InventoryManager Sewer Supervisor Financial Manager
Uses spreadsheet as guide for making adjustments inPeopleSoft
Copies information fromemail to adjustment spreadsheet
Clarifies information for financial manager. Makes changes as required for approval.
Sends spreadsheet to financialmanager for approval on adjustments
Yes
No
Runsmonthly report toverify all adjustments madewere approved.
End
Sends email reply to
Adjustments approved?
inventory manager
Inventory–CycleCount
SewerMaintenance
Start
Createandprint reconciliation reports for all vehicles. Give to Asst. Sup’t.
Sendall count sheets toPUAdmin for data entry
Enters stock quantity update approval in PS
Print and collate (re)count sheets for all vehicles.
Prepares countingevents inPSdaybefore countsbegin
Dispense count sheets toassistant superintendent(s)
End
Superintendent InventoryManager Assistant Superintendent Sewer Supervisor
Sign reconciliation report and return to inventorymanager for stockquantity update
Approveof reconciliation report?
No
Yes
No
Yes
Disseminate count sheets toall supervisors for actual counting
Approveof reconciliation report?
Count inventoryon vehicle; handall counts sheets in to inventorymanager
Inventory– Issuance
SewerMaintenance
Start
Go towarehouse topick up required inventory
RequirePPEpickup?
No
WarehouseEmployee Sewer Employee InventoryManager SafetyOfficer
Issues paper copyofMSR toemployee. Retains signed copy
RemovePPE from inventory request
Issues inventory to sewer employee
Yes
Use report from query to receive inventory inPS to trucks inventory
Checks PSquery for open interunit inventory
No
End
Yes
Employee cleared to pickupPPE?
MiscellaneousAction
SewerMaintenance
Dailywork entered into spreadsheet
Workorder entered intoHansen
End
Sewer Crew Sewer Supervisor Assistant Superintendent Start
Notifiesproper division (Water dist. StreetMaint, etc)
Notifies crews supervisor to relay locationand information
Receives assignment
End
End
Yes
Notifies supervisor of remainingwork for different crew
Yes
Completespaperwork order
Recieves locationand assignment from supervisor.
Arrives at location, assesses equipment and material requirements
Outside resources required?
Different crew required?
Notifies supervisor of work completion
No
Completeswork
No
SSOResponse
SewerMaintenance
Start
Receives call about suspected SSO
Dispatch/Staff Support
No
Notifies required agenciesof spill, volume, cleaning completedand samples
Receives call from dispatchwithall pertinent information
SSOeffluence reach surface water?
Volumeof effluent inwater toohigh?
No
End
ORC
Assistant
Superintendent/
Notifies homeowner that plumberwill need tobe contacted for repairwork
Sendsnearest flush crew togivenarea
Sewer Supervisor FlushTruckCrew Easement/MitigationCrew Investigates and verifies SSO
Private
Privateor Public main?
Cleanout
Yes
Public
Fillsout paperwork order
Flushesmainuntil relief is achieved
Mainor Clean out?
Yes
Notifies supervisor of locationand verifiesmain/ manhole(MH) overflowing
Main
Placedon standby pending volume calculations
Performblocking and cleaningon effluence
SmokeTest
SewerMaintenance
Receives request for sewermain smoking (via email,work order or citizen call)
Paperwork order entered intoHansen
Dailywork entered into spreadsheet
End
Start
Sewer Crew Sewer Supervisor Assistant Superintendent
Receives location for smoking from assistant superintendent
Notifiesoriginal requestingpartyof crews findings
Fillsout paperwork order andnotify supervisor of findings
Receives location from supervisor. Arrives at location
Notifies FireDept. andhome/business owner (if applicable)
Setup smoke machineand smokes line
Easement ClearingOverview
SewerMaintenance
Assign crew to basin(s)
Start
Tabulatesmonthly/ yearlydata from maps and forms
End
Create ‘Clearing CrewMapBook(s)’
Easement ClearingSupervisor Easement ClearingCrew
Performeasement clearing
Notate ‘Clearing CrewMapBook’
PreventativeMaintenance
WaterDistribution
Completed Spreadsheet Updated
HansenWorkorder Created
FieldCrew Supervisor AdminSupport
ReviewPM Form
Start
Water AssetsAssignment
Listening Surveys LeakDetetection
ExercisingValves
ServicingHydrants
InitiatePM Form
FurtherWork?
No
End
Treated Sameas MainBreak
Yes
Yes
Emergency?
RepairWork ForwardTo FieldCrew
No
Water LeakProcess
WaterDistribution
Start
IssueReported
OtherDepartments AdminSupport FieldCrew Supervisor Call Taker Supervisor II
LeakDetected?
No
CustomerNotified
End
ReviewsWorkOrder Entries
Yes
Yes
Initiate workorder via Repair Form
SecureMaterials and Dispatch
Sitework completed?
Completed Spreadsheet Updated
No
HansenWorkOrder Created
Emergency Transportation
PublicAffairs CityManager PublicWater Supply
StreetsDept for Patches
Water PlantNotified
Merger Towns FireandPolice
End
Hydrants, Blow-Off Valves, andServicesRepair
WaterDistribution
Start
ProblemReported
AdminSupport Hydrant Crew FieldCrew Supervisor Call Taker
Yes
Hydrant or other water node?
Hydrant
Out of Service?
Notify FireDepartment
No
Other
Repair FormReviewed
Repair or Replace?
Replace
Repair
Crew replaces hydrant
SiteWorkCompletedby DigCrew
Repair form initiated
SiteWork Completedby Hydrant Crew
Repair form initiated
WorkOrder in HansenCreated
Spreadsheet Updated
End
Locator Process
WaterDistribution
Evaluates locations bypriority
Start
Locator Supervisor
Highor lowpriority?
LowPriority
Unlikely tobe located
End
HighPriority
Feedback toWEB TMS
Feedback if other City dept. has requested locate
LocateCompleted
End
Water ServiceRequests
WaterDistribution
Email sent to Water Distribution
Customer Initiates ServiceRequest
Start
Meters AdminSupport FieldCrew Supervisor PUAdmin
Install form reviewed
MeetwithHomeowner/ Contractor
SiteWork Completed
Install form initiated
HansenWorkOrder Entry
Spreadsheet updated
End
Notification thatwork is complete
Soil Sampling
LandManagement-NRWWTP
Supervisor completes appropriatepaperwork
Receive results from lab
End
for Environmental MonitoringTech.
Supervisor II L.M. Supervisor EquipmentOperator III Start
Choose soil sample tobe taken
Place sampleboxes in shipping container
Make samplebox labels
Fill soil boxes and label appropriately
Placedon tables with field ID numbers
Samplesdryon tables in shop
Samples shipped to lab
Take soil sample
PlantingPreTillage
LandManagement-NRWWTP
Disk land to chop and level
Run field cultivator to finish leveling
End
Soybeans, Sorghum Wheat, andFescue
EquipmentOperator III Supervisor II Start
Rip landwith terrogators *no liquid
Disk field to chop and level
Run field cultivator to finish leveling
End
Corn
Typeof Crop
PlantingCrops
NeuseRiverWWTP
Corn
If seeddepth is correct, continue planting specified average
SetDrill andRow Morters to correct setting
Plant 100' digup seed to check seed depth
MakeChanges to setting if needed to get proper depth
Soybeansaand Sorghum
SetDrill toSpecific CropSettings
SetDepthand ClosingWheels
FillwithSeeds
End
EquipmentOperator III Supervisor II LMSupervisor Start
Wheat
DetermineCropand CheckWeather
Approval of Crop
Irrigation
LandManagement-NRWWTP
Determine zones, Runtimes. Check fecal, turbidity, 24hr rainfall andenter information into Irrigation logbook
Enter logbook into materialmanager. Entermaterial manager data into irrigation scheduler
After zones completed take meter readingand recordend time
Downloadandenter Rn/Et data into Irrigation schedules
Contact operations staff to turnon pumps
Openmain irrigation valve toallow lines to fill
Monitor SCADA to verifypumps are in autoandareat idle
Start ICC. Record start timeandmeter reading
Verify that zones are properly runningvia visual inspection
Upon completion call operations to shut downpumps
Setupprograms in ICC
Start
End
Operations Supervisor II
Closemain irrigation valve
Turnpumps toauto
Shut downpumps
SprayingChemicals
LandManagement-NRWWTP
Document state regulations info into book
SwitchonGPS to insure connection to Satelites
Set rateon controller anddrive to field
SetApoint andB point then follow lines to spray
Notification isput in field for reentry times
Add chemical and fill withwater
Fill out reuse sheet
Supervisor II EquipmentOperator III Start
Determine current conditions and how to proceed
Notifiedof completion
End
HarvestingGrain
LandManagement-NRWWTP
Change combine crop settings
Harvest½of a combinehopper
CheckMoisture
HighMoisture
LowMoisture
When truck is empty, turnoff pit toauger andauger towet bin
If needed, change minor settings to adjust
Pull over thepit, turnonauger towet binandpit toauger
Takegrain sample while truck is dumping
Test andwrite moistureand bushelson tickets
Harvest 2 to4 round in field
Perform combine loss test in the field
Weighand ticket the truck
Opendoor and dumpgrain
Continue toharvest
End
EquipmentOperator III Supervisor II Start
End
Yes
NoHarvest
No
Checkweather and 48hour rainfall
RunDryer?
GrainHandling-Bin toCustomer
LandManagement-NRWWTP
Pull toappropriate binandbegin loading
After the trailer is full,weighand ticket the truck
Weight and ticket the customer
Sign contractor grain ticket
Start
Supervisor II EquipmentOperator III AdminStaff Suppot
Review tickets and payment
PaymentHandling
End
ClassA Loading
LandManagement-NRWWTP
Temperatureand Hach/Wimmsdata within requirements?
Supervisor signsoff for tempand fecals inHach/Wimms
IDFlagplaced into pile, notifying Land Management that pile is ready tobe moved
Yes
24hr fecal sample taken frompileand sent to lab
Batchbeing made
Start
Yes
No
LandManagement Operations Lab
Notify supervisor
ReviewHach/ Wimms for signatures from lab andoperations supervisor
Movesbatchonto pad inawind row and replaces IDFlag inpile
Notifyequipment operator that batch is released
Replace IDFlagwith larger green flag
Equipment operator “Scarab’s” thebatch
EO3 loadsout Class A
End
Testsbatch for fecals, nutrient and metals. Entersdata in toHach/Wimms
Supervisor signsoff
ClassB Loading
LandManagement-NRWWTP
Activatepumps in SCADA. Land
Management staff now have remote control of pump station.
Shut downpumps
End
EquipmentOperator III Operations L.M. Supervisor Start
Truck is loadedand volume, date, time and field indicator are recordedon load sheet
Truck isdirected under the load station tobegin loading
Truck leaves and goes topre- determined location for offloading
NotifiesOperations staff of completed loadingat theendof theday
Inspectionof truck andpaperwork is completed
Truckpass inspection?
Yes
No
Trucknot loaded
End?
Contactsoperations staff toask for ClassBpumps tobe turnedon. Gives all fielddata tooperations to be stored inSCADA
LimeApplication
LandManagement-NRWWTP
ClassAorAg Lime?
Start
LandManagement Supervisor EquipmentOperator III Contractor Supervisor II WarehouseSupervisor
ClassA
LoadContractor’s equipment
Escort Contractor to site
Ag
Deliver Product
SpreadMaterial
End
GatherQuotes
Receipt ofMaterial
Vendor delivers material
P.O. Created
PartsOrdering “EquipmentOnly”
LandManagement-NRWWTP
Part ispickedupand brought toNR WWTP
Requiredpart is determined
Part priceunder $1000?
Quotes aredrawn upand sent toVFS
Installationof part is scheduled
Start
No
End
Yes
VehicleFleet Services HeavyEquipmentMechanic
VFS calledor e- mailed, communicating need for part
Determinesmethod of payment for part (Dana inVFSdecides this)
Part isobtainedby VFS
Part(s) isordered
PlantMaintenance
NeuseRiverWWTP
Staff hasdetailed checklist andmapof zones (providedby supervisor)
Inspects all equipment prior to use
Completes zoneper checklist and reports to supervisor
Washand fuel equipment for next day
Moveson tonext zone
End
Supervisor II Support Specialist Start
Notifiedof incomplete zone
No
Assigns staff to designatedwork zones
Inspects completed zones
Zone completed?
Yes
End
CheckingCans
NeuseRiverWWTP
Dropempty can besidebuildingand pull full canout and dropoutside
DumpWalnut Creek full can into ragpile anddropemptied canat yard
Dumpbothgrease cans in ragpile then place themunder chute
Drive togrease cans andpull plugs to begindrainingwater
Drive toBarwell withanempty can on truck
Placeempty can under screwand pickup full can
PickupWalnut Creek emptyand leaveon truck
Park truckback under shelter
Start
End
EquipmentOperator III
MOCProcess
NRWWTP
Closer of associatedCAPA createsMOC& decideswhichprograms areaffectedby the changes, andnumbersMOC. Number is sameasCAPAwith “MOC” added toend.
SendsMOC toPTCO via email.
MOC is closedand sent toPTCO
Start
PTCO IssuingManager Management TeamMember EMSCoordinator
Facilitates signaturesby affected staff members
PDF copyof closedMOC isput in appropriateprogram folder under close inMOC folder on sharedrive. PreviouslyopenedMOC ismoved toarchive folder.
Moves electronic copyof MOC intoappropriate folder for programunder OPEN inMOC folder fund on the sharedrive
Makes changes toDOPon sharedriveand confirm completionof trainingafter verifying signatures
SignMOCand return toPTCO
Managesprocess. Updateson status aregivenatmonthly meetings
End
CAPAProcess
NRWWTP
Copy&Paste closed CAPA into appropriate program folder on the sharedrive
Move “opened” CAPA form fromOpen toArchive.
Copy&Paste the newlyopenedCAPA intoappropriate program folder on the sharedrive
Reviewand signoff onCAPA. This actionwill close the CAPA
Fill out CAPA formdetailing what theproblem is,who it is assigned to, date, and appropriate IDnumber.
Requirean MOC?
No
Start
Yes
IssuingManager AssignedEmployee EMSCoordinator
MOCProcess
Senda copyof the completedCAPA form to issuing manager.
Complete appropriate
correctiveactionor training. Document asneeded.
Managesentireprocess. Updatesmanagement teamatmonthlymeetings. What CAPAs areopenand how theprocess is going
End
PartsOrdering
NRWWTP
Call vendor andget 3quotes if parts are more than$1000. If less get a single quote
Gather correct parts informationand createa list
Sendquote toVFS for approval
Pickupparts and take invoice toVFS.
End
Start
L.M. Mechanic Vendor VFS
Vendor callswhen parts are ready for pickup
Approveparts and call vendor toorder parts
InventoryProcess –LandManagement EquipmentMaintenanceProgram
NRWWTP
On invnetory stock sheet placeproper color sticker on sheet. Yellowor red
Removepart from inventory
Start
Locatepartsneeded
Supervisor II L.MEmployee Mechanic
Part requires reorder
StickerRed?
Yes
No
Parts receivedand put back into inventory. Green sticker placedon inventory sheet
Mechanicdoes audit on inventoryparts
Orders required parts
End
MaintenanceRequest –LandManagement EquipmentMaintenanceProgram
NRWWTP
Fill outMaintenance Request Form
Start
Employee Supervisor Mechanic
WorkOrder is completeand electronic copy sent tomechanicby email
Reviews Maintenance Request
AreParts Needed?
Parts arepulledand equipment repaired
Mechanic Needed?
No
Yes
Yes
Mechanic WorkProcess
No
End
Enter intoFaster Software
End
MechanicWorkProcess –LandManagement EquipmentMaintenanceProgram
NRWWTP
SendE-mail detailingwhat is wrong, equipment number, location, and list of partsneeded. Attach copyofmaintenance request.
Start
Utilities Supervisor II Mechanic
Createworkorder andassign the appropriate status: Active Inactive Part Status (Waiting onparts)
Work is completed andworkorder is closedout
Parts List Correct?
Yes
Parts areordered
Parts arepickedup
End
No
Equipment is brought into shop, parts are determined
CorrectiveAndPreventiveActionProcess (CAPA)
NRWWTP
Fill out CAPA form fields Date, Requestedby, ProblemStatement, Correction Immediate Action, ProbableCause, ContributingFactors
Nonconformance Noncompliance Emergency Other Problems
Evaluation if CAPA is necessary
Start
Yes
No
Requestor (Anyone) Issued (Assigned) Employee EMSCoordinator CAPAManager
End
Move “opened” CAPA form fromOpen toArchive folder.
Review, add info, assign, copy&paste CAPA into appropriate program folder on sharedrive
Copy&Paste closed CAPA into appropriate program folder on the sharedrive
Reviewand signoff onCAPA. This actionwill close the CAPA
Requirean MOC?
No
Yes
MOCProcess
Senda copyof the completedCAPA form toCAPA manager.
Completeappropriate solution. Documents asneeded.
E-mail notification
Managesentireprocess. Updatesmanagement teamatmonthlymeetings. MaintainsCAPAStatus Tracking Log.
Of CAPA creation
END
Management of ChangeProcess (MOC), CorrectiveandPreventiveActionPlan (CAPA)Generated
NRWWTP
CreatesMOC if requiredbyCAPA. Fill out MOC form fields, date, requestor, proposed change, purpose,modifications, timeframes.
SendsMOC toPCTO via email.
Reviews, signs, dates and closes MOC
Start
ProcessControl TrainingOfficer PCTO CAPAManager Management Team Members EMSCoordinator
Facilitates signaturesby affected staff members
ScannedPDF copyof closedMOC is put inappropriateprogram closed folder on sharedrive. Previously openedMOC ismoved toarchive folder.
Moves electronic copyofMOC into appropriate folder for programon the sharedrive
Makes changes toDOP’son sharedriveand confirms completionof trainingafter verifying signatures
Authorizers review, dateand signMOC and return toPCTO
Programmembers reviewand sign MOC
UpdatesCAPA tracking form. Updateson status aregivenatmonthly meetings
E-mail notification ofMOC
End
SolidsHandlingProcessOverview
NRWWTP
LimeBlender RaleighPlus
Pad
Start
Primary
DayTanks
Dewatering
Hoppers Dewatered Cake
? SolidsRemoval Required
End
No
CADTank
WAS
UNCAD
Thickening
LandManagement Operations Lab Admin Biosolids Production Planning Yes
Distribution
Distribution
Distribution
Pass
Pass
Pass Fail
Pass Fail
Fail
Fail
Yes
RaleighPlus DewateredCake
Yes
ClassB Liquid Fail
RaleighPlus Fail
No
ClassBLiquid
IssuingTools
NeuseRiverWWTP
Tool signed out to employee in MaintStar
Tool is returned to warehouse physically
MainStar Database Updated
Tool is taken from warehouse
Inspects tool upon return
Is tool inworking order?
Yes
End
Plant Employee WarehouseStaff Start
MainStar DatabaseEntry
No
Employee makes repair or informs supervisor of issue.
Employeeneeds tool housed in warehouse
Tool brought back to warehouse
Tool isused
FuelsManagement (throughPU)
NeuseRiverWWTP
Receivedelivery ticket, sent toAdmin Support
Fuel purchased from vendor. Alwayson POor publicutilities account
Amount of fuel needed is determined
Levelsof fuel tanks are read
Supervise fuel off- load
Start
Is fuel needed?
Yes
End
WarehouseStaff Vendor
No
End
Receivespayment anddelivers fuel
FuelsManagement (throughVFS)
NeuseRiverWWTP
Request for fuel needed is sent to purchasing (e-mail)
Receivedelivery ticket
Amount of fuel needed is determined
Levelsof fuel are read
Supervise fuel off- loading
Start
Is fuel needed?
Yes
End
WarehouseStaff Purchasing Vendor
No
End
Placeorder for fuel underVFS account
Deliver fuel
Non-Inventory ItemPurchasing
NeuseRiverWWTP
Receivesorder and payment
Entering aPart intoMainStar
Part delivered
Vendor WarehouseStaff Plant Employee Start
Start
Parts checked indaily
Partsorder information ispulled from cabinet
Purchaseneeded part. Payment dependsonpriceof part.
Part entered intoMainStar
Employee isnotified that part is ready for pickup.
Parts Infoentered intoMaintStar under assigned non-stock number
Part is keyed toworkorder it hasbeen assigned to in MaintStar
Employee isnotified part has arrived
Picksuppart
End
End
CycleCounts
NeuseRiverWWTP
Monthly inventory report generated for 1/12ofwarehouse inventoryusing MainStar
Visual inspection performed to validateprinted report
Count and reportmatch?
Report to superintendent.
Start
Yes
WarehouseStaff Superintendent
No
Investigatewhy report is not correct. Determine if errors arewithin acceptable levels. Correct andadjust report
Reviewmonthly reports
End
StockReplacement
NeuseRiverWWTP
Items are purchased. Payment type dependson value
Minimumbalance report rundaily usingMaintStar
Parts entered intoMainStar
Partsphysicallyput away inwarehouse
Start
Report is reviewed
End
WarehouseStaff Vendor
Receivesorder and payment
Parts aredelivered
IssuingParts
NeuseRiverWWTP
Part is given to employee
Start
Requestspart
Plant Employee WarehouseStaff
Fillsoutwarehouse issuing ticket
Warehouse issuing ticket charged to workorder, program, truckor employee
Check inventory for part
Pullspart from warehouse
Part in stock?
Yes
End
No
Non-Stock item purchasing
End
Made with FlippingBook