Caldbeck Dr
Easement Work Plan
CORPUD Sewer Maintenance Division
Caldbeck Dr. Easement Restoration Phase 3
AREA OF OPERATION
AFFECTED CITIZEN NOTIFICATION
1909 CARRBRIDGE WAY
8401 CALDBECK DR
SALISBURY PARK HOMEOWNERS ASSOCIATION
8121 BLUFFRIDGE DR
INCLUSION ZONE
INCLUSION ZONE
SCOPE OF OPERATION
BANK RESTORATION 2
TEMPORARY CREEK CROSING 1
DEBRIS REMOVAL
CONSTRUCTION ENTRANCE
BANK RESTORATION 3
TASK EXECUTION ORDER
1. WZTC 2. CONTRSUCTION ENTRANCE / SUPPLY STAGING AREA
3. *TEMPORARY CREEK CROSSING 1 4. *TEMPORARY CREEK CROSSING 2 5. *TREE REMOVAL 6. *BANK RESTORATION 1 7. REMOVE TEMPORARY CREEK CROSSING 2 8. *DEBRIS REMOVAL 9. REMOVE TEMPORARY CREEK CROSSING 1 10. *BANK RESTORATION 2 11. *BANK RESTORATION 3 12. FINAL RESTORATION 13. CONSTRUCTION ENTRANCE REMOVAL 14. WZTC REMOVAL
TEMPORARY CREEK CROSSING 2
BANK RESTORATION 1
TREE REMOVAL
* Denotes a specific Work Order
WZTC Requirements
Description
A
A - UTILITY WORK AHEAD
A / 600 ft. north of intersection of Carrbridge Way and Briegeport DR. A2 / 600 ft. south of intersection of Carrbridge Way and Briegeport DR
B
B - LANE NARROWS (optional)
+150 ft south bound of WZTC A
C
C - BE PREPARED TO STOP
C / +150 ft south from WZTC B C2 / +200 ft north bound from WZTC A2
F
D
D - FLAGGER AHEAD
• Intersection of Carrbridge Way and Briegeport DR. • Flagger applicable only for controlling constructions vehicles and equipment arriving and departing from construction entrance • D /-150 ft south bound WZTC C • D2 / +600 ft north bound WZTC A2
E
D2
F
E - CONSTRUCTION ENTRANCE (optional)
C2
F -Channelizing devices set for narrow lane and roadside staging area om ROW
Utilize MUTCD for proper placement of channelizing devices based on 35 MPH posted speed limit Use TA-6 Ensure that there is at least 10 ft. of ROW for undisrupted traffic flow
A2
PROPOSED WZTC
PROPOSED CONSTRUCTION ENTANCE
TEMPORARY CREEK CROSSINGS
TCC-1
TCC-2
TREE REMOVAL SITE
BANK RESTORATION 1
DEBRIS REMOVAL
BANK RESTORATION 2
BANK RESTORATION 3
FINAL RESTORATION