PU Monthly Report Volume III Issue II-August
CITY OF RALEIGH PUBLIC UTILITIES Monthly Performance Report FY 15 (July 2014-June 2015)
EMJ WTP PROJECTS
Project Manager
Current Phase
Completion Date
Project Name
Vendor
%
Status
FLOCC & Sed. Basin Full Scale Pilot
ES
Design
Hazen & Sawyer 95%
11/2014
Continuing Design
Raw Water Reservoir Cover
PA
On Hold
-
0%
-
On Hold
Sodium Permanganate Improvements
DWSRF Application for 0% Loan Approved
PA
Design
Hazen & Sawyer 95%
12/2014
Brown and Caldwell
Clearwell Assessment Diving Complete
Clearwell Rehabilitation
RR
PER
17%
-
Wastewater Collection and Pumping Improvements (Phase II)
PA
On Hold
Jacobs
-
-
Reassigning Contract
Municipal Engineering
Warehouse Expansion
PA
Design
100%
9/2014
Bid Date August 2014
Raw Water Reservoir Sludge Removal
PA
On Hold
-
-
-
-
UV/Solids Handling
PA
-
-
-
-
-
DE BENTON PROJECTS
Project Manager
Current Phase
Completion Date
Project Name
Vendor
%
Status
Settling Tank Dewatering Facilities Wrenn Road Lagoon Improvements
Advertise RFP/RFQ August 2014
DL
PER
Jacobs
95%
9/2014
Water & Waste Construction Wharton-Smith, Inc.
Demonstration/Substantial Completion
DL
Construction
95%
9/2014
Backwash Waste Recycling Facility
PA/RR
Construction
50%
12/2014
-
Hazen and Sawyer
DEB Reservoir
EN
Design
-
-
Received SUP February 2014
22
All financial data is from the city’s financial management system. This is an unaudited report.