PU Monthly Report Volume III Issue II-August
CITY OF RALEIGH PUBLIC UTILITIES Monthly Performance Report FY 15 (July 2014-June 2015)
SEWER MAIN REPLACEMENT PROJECTS
Project Manager
Current Phase
Completion Date
Project Name
Vendor
%
Status
Reviewing 95% Plans 90% of Main Interceptor and 100% of Laterals Added Section of Sewer Replacement on Hold until July Project Information Meeting in August Working on Tunnel at Burgess
Sanitary Sewer Siphon Rehabilitation
RR
Design
Hydrostructures 95%
9/2014
Centurion Construction
Marsh Creek Sanitary Sewer Replacement
RR
Construction
95%
9/2014
Chamberlain, Clark SS Replacement
ES
Construction
Moffat Pipe
70%
3/2015
Hammond Rd SS Relocation
RR
Scoping
Dewberry
-
TBD
Gorman St. Sewer Rehab./Replacement
AB
Construction
Moffat Pipe
35%
12/2014
Desktop Review Extended Submitted to Development Review N-T-P February 2014
Aerial Crossing Replacements II
RR
PER
URS
75%
-
Aerial Crossing Replacements I
RR
Design
Dewberry
90%
-
Leafcrest Sewer Realignment
AB
Construction
Moffat Pipe
0%
12/2014
City Coordination Meeting in August
Lake Wheeler Rd Stream Relocation
RR
Design
Kimley-Horn 60%
1/2015
Flow Monitors Removed, Report Underway
Beaman Lake Creek Interceptor Evaluation
JG
Study
Hydrostructures 50%
-
Upper Pigeon House Sewer Interceptor Replacement
Advertisement in August
EN
Design
GHD
100%
2/2016
Ashe Av/Park Av/Cox Av Water and Sewer Replacement
JF Wilkerson Contracting
DL
Construction
0%
4/2015
N-T-P July 2014
Negotiations and Settlement
Eton Rd Sewer and Aerial Replacement
DL
Design
Aecom
100%
4/2014
Edens Land Corp.
Seaboard Station Sanitary Sewer Evaluation
AB
Planning
0%
12/2014
Scoping
Lower Marsh Creek Interceptor Evaluation
RR
PER
Hydrostructures 100%
6/2014
Complete
North Hills Dr, East St, E. Lenoir, Corporation Pkwy CCTV Investigation
DL
Design
Hydrostructures 50%
11/2014
Design in Process
23
All financial data is from the city’s financial management system. This is an unaudited report.