CITY OF RALEIGH PUBLIC UTILITIES Monthly Performance Report FY 15 (July 2014-June 2015)
WATER MAIN REPLACEMENTS
Project Manager
Completion Date
Project Name
Current Phase
Vendor
%
Status
Design of Water and Sewer Replacement
2012 Water Line Replacements #2
ES
Design
McKim & Creed 50%
9/2014
Mack Todd Rd. & W. Gannon Improvements
JG
Design
Edens Corp.
90%
TBD
Design in Progress
Informal Bidding August 2014
Aurora Dr Bridge –WL Replacement
RR
Prebid
-
-
-
Centurion Construction
Final Change Order August 2014
2011 Water Line Replacements #3
RR
Construction
98%
9/2014
2011 Water Line Replacements #4A
JG
Construction
Moffat Pipe
0%
-
Contract Routing
Contracts Routing for Combined Project Design of Water and Sewer Replacements Design of Water and Sewer Replacements Design of Water and Sewer Replacements Design of Water and Sewer Replacements Design of Water line Around Cargill Plant Design of Water and Sewer Replacements Design of Water and Sewer Replacements
2012 Water Line Replacements #3
ES
Construction
TA Loving
0%
10/2015
The Wooten Company The Wooten Company
2012 Water Replacements #3A
ES
Design
12/2014
2012 Water Replacements #3B
ES
Design
40%
2/2015
2013 Water Line Replacements #1
ES
Design
AECOM
90%
11/2014
Highfill Infrastructure Highfill Infrastructure Highfill Infrastructure
2013 Water Line Replacements #2
ES
Design
95%
10/2014
2014 Water Line Replacements #1
ES
Design
0%
5/2015
2014 Water Line Replacements #2
ES
Design
0%
8/2015
2014 Water Line Replacements #3
ES
Design
McKim & Creed 95%
8/2015
WATER SYSTEM IMPROVEMENTS
Project Manager
Completion Date
Project Name
Current Phase
Vendor
%
Status
DEBWTP Garner Water Mains
PA
Design
Arcadis
100%
9/2014
Bid August 2014
Hazen and Sawyer
Field Work Complete
Master Plan Update
EN
Pre-Design
40%
1/2015
Springdale Tank Replacement
EN
Pre-Design
Wooten
0%
-
Kick-Off
Wendell Blvd Water Main Extension
RR
Design
McKim & Creed 90%
9/14
Plans in Review
27
All financial data is from the city’s financial management system. This is an unaudited report.