CITY OF RALEIGH PUBLIC UTILITIES Monthly Performance Report FY 15 (July 2014-June 2015)
NCDOT/PUBLIC WORKS CONFLICT PROJECTS
Project Manager
Current Phase
Completion Date
Project Name
Vendor
%
Status
Pre-Con August 2014 Hammond Rd Agreement Public Meeting September 2014
NCDOT U-4432 Tryon Road
JG
Construction
NCDOT
0%
-
NCDOT Vaughn Melton
NCDOT I-440 Crawleigh
JS
Coordination
10%
-
Public Works Hillsborough Streetscape
JS
Design
Kimley Horn
65%
-
Public Works Capital Blvd.-Spring Forest to Old Wake Forest Public Works South and Lenoir 2 Way Conversion
JS
Design
-
10%
-
-
Additional Survey Needed Transportation Bonds Approved
JG
Design
Kimely Horn
40%
-
Public Works Mitchell Mill
JG
Design
Kimley Horn
75%
-
NCDOT Capital Blvd (Peace St. to Wade Ave)
EN
Design
-
-
-
-
MISCELLANEOUS PROJECTS
Project Manager
Current Phase
Completion Date
Project Name
Vendor
%
Status
Little Creek WWTP Filter Rehabilitation
DL
Construction
Aqua Aerobics
-
Contracts Executed
-
Little River Reservoir Draft EIS
KW
Planning
Hazen & Sawyer 75%
6/2014
Draft EIS in Process
Telemetry System Improvements Ph. III Smith Creek WWTP Maintenance Building
Construction (Phase 3)
Crown Castle Lease Needed Completed Under Slab Utilities Completing Final Draft
PA
CITI
97%
9/2014
ES
Construction SBC Construction 65%
12/2014
Sewer Capacity Study
JS
Study
Black and Veatch 99%
Complete
Substantial Completion
UFOC East and West Lot Improvements
JG
Construction Riley Contracting 90%
10/2014
EMJ - Phase II- 90%, Falls Lake Compiling Laboratory Data
VA Security Improvements Phase I & II
PA
Construction
CITI
95%
9/2014
Central Laboratory Study
DL
Study
Hazen & Sawyer 90%
9/2014
Interior Architecture
Utility Billing Renovations Lake Woodard
JG
Design
10%
-
Space Study
East Operations
JG
Design
DTW Architects 50%
-
28
All financial data is from the city’s financial management system. This is an unaudited report.